title: "Alternative Finished Goods"
space: "ERPNext"
url: "https://docs.frappe.io/erpnext/alternative-finished-goods"
updated: "2026-08-28"
---

## **Problem**

In process industries (e.g. chemicals), a Work Order sometimes produces a sellable item that differs from the expected finished good, a different grade or specification identified during QC. It is not scrap but also not the expected finished good. 

## What is this feature?

With this feature you can, in one click, tell ERPNext: *"This Work Order actually produced Item B instead of Item A."* The system creates a stock entry that is **linked to the Work Order**, moves the stock from the planned item to the actual item, carries the production cost over, and shows the real output in production reports.

## When should you use it?

Use **Change Finished Item** when **all** of these are true:

- The Work Order is submitted and some quantity has already been produced.
- QC (or any inspection) found that the output is a **different but sellable item** — a different grade, purity, or specification.
- The actual item is one of the pre-approved alternatives of the planned item.

Do **not** use it when:

- The output is waste or scrap → use the normal scrap flow instead.
- You simply produced less than planned → use process loss.
- You want to repackage into different pack sizes → use a normal Repack Stock Entry.

## Real-life example

**Sunrise Chemicals** runs a Work Order to produce **100 kg of Epoxy Resin – Grade A**.

Production completes and 100 kg is booked into the Finished Goods warehouse. During QC, the lab finds that **20 kg** of the batch does not meet Grade A viscosity limits — but it fully meets **Grade B** specification, which the company also sells (at a lower price).

Without this feature, the store keeper would make a manual Repack entry that has no link to the Work Order — reports would forever say "100 kg Grade A produced", which is wrong.

With this feature, the supervisor opens the Work Order, clicks **Change Finished Item**, selects *Epoxy Resin – Grade B* and enters *20*. ERPNext:

- removes 20 kg of Grade A from the FG warehouse,
- adds 20 kg of Grade B in the FG warehouse **at the same production cost**,
- keeps the entry linked to the Work Order,
- and the **Work Order Summary** report now shows: `Grade A: 80, Grade B: 20`.

---

## One-time setup (Manager)

### Step 1 — Turn the feature on

Open **Manufacturing Settings** and enable **Allow Alternative Finished Goods** (in the *BOM and Production* tab), then save.



![](/files/Screenshot 2026-08-28 at 12.15.17 PM.webp)

### Step 2 — Allow alternatives on the planned item

Open the **Item** you normally produce (e.g. *Epoxy Resin – Grade A*) and enable **Allow Alternative Item**, then save.

### Step 3 — Define the allowed grades

Create an **Item Alternative** record for each grade the process may produce:


| Field                 | Example value                                                    |
| --------------------- | ---------------------------------------------------------------- |
| Item Code             | Epoxy Resin – Grade A *(the planned item)*                       |
| Alternative Item Code | Epoxy Resin – Grade B *(the possible actual output)*             |
| Two-way               | Tick only if Grade B Work Orders can also be regraded to Grade A |


![](/files/Screenshot 2026-08-28 at 12.26.21 PM.webp)



Setup is done. You never need to repeat this unless a new grade is introduced.

## Daily usage (Operator / Supervisor)

- **Finish production as usual.** Complete the Work Order's Manufacture entry so the produced quantity is booked.
- **Open the Work Order.** After QC identifies a grade change, open the Work Order and click the **Change Finished Item** button.

![](/files/Screenshot 2026-08-28 at 12.25.21 PM.webp)

- **Fill the dialog.**

![](/files/imagefe13aa.webp)

- **Actual Finished Item** - System will auto default when there's only one alternative or pick the grade QC approved (only pre-approved alternatives are shown).
- **Qty to Convert** - how much of the produced quantity is actually the other grade. The dialog shows how much is available to convert.

  

  
- **Create Stock Entry.** 
  - In the popup, you will see Create Stock Entry, click on it and ERPNext opens a ready-made draft Repack entry. Fill in the **batch / serial numbers** for both rows (the batch being consumed and the new batch being created), then **Submit**.

  
- **Check the report (optional).** Open **Work Order Summary** — the *Actual Finished Goods* column shows the true output

![](/files/Screenshot 2026-08-28 at 12.31.40 PM.webp)

## Good to know

- **Cost is transferred automatically.** The actual item is valued at the same cost the Work Order produced — no manual rate entry needed.
- **You cannot convert more than was produced.** The system tracks earlier conversions and blocks anything above the remaining produced quantity.
- **Quantity in = quantity out.** The converted quantity and the new item's quantity must match. (For genuine quantity-changing operations, use a normal Repack entry.)
- **Partial conversions are fine.** You can convert 20 kg today and another 10 kg tomorrow, as long as the total stays within the produced quantity.
- **Wrong entry?** Cancel the conversion Stock Entry - stock and cost return to the planned item, and the converted quantity becomes available again.
- **Nothing changes if the feature is off.** The button and report column appear only when *Allow Alternative Finished Goods* is enabled in Manufacturing Settings.

---